    HomeTelanganaKothapalli-Manoharabad railway line set to start by 2027

    Kothapalli-Manoharabad railway line set to start by 2027

    Related stories

    CM Revanth announces multiple benefits for tribals

    Hyderabad: Chief Minister A. Revanth Reddy announced several welfare...

    Whales Purchase 470 Million Dogecoin: Is it a Good Time to Invest in DOGE?

    The post Time to Buy DOGE? Whales Buy 470 Million Dogecoin appeared first on Coinpedia Fintech News Amid the ongoing market recovery, Dogecoin (DOGE) appears promising as whales show strong interest and confidence in the world’s largest meme coin. Whale Buys 470 Million DOGE On January 11, 2024, a prominent crypto expert posted on X (formerly Twitter) that crypto whales have purchased a significant 470 million DOGE in the past 48 hours. …

    SpinSci Health Tech India to Create 1,000 AI Jobs in Telangana

    SpinSci Health Tech Announces 1,000 AI Jobs in TelanganaSpinSci...

    Asha Workers Protest at Jadcherla MLA Office Over Salary Hike and Benefits

    Asha Workers Protest for Better Pay and Working Conditions...

    Union Minister Highlights Progress on Kothapalli-Manoharabad Railway Line

    Hyderabad: Union Minister of State for Home Affairs, Bandi Sanjay Kumar, announced that the Kothapalli-Manoharabad railway line would provide an alternative route to New Delhi in case of disruptions or accidents on the Secunderabad-Kazipet railway line. This project, he said, will further improve connectivity in Telangana. During his visit on Friday to Karimnagar Railway Station and other railway projects in his constituency, he reviewed the progress of the long-awaited Kothapalli-Manoharabad railway line. This project has been a long-cherished dream for the people of the former Karimnagar and Medak districts.

    - Advertisement -LandSeeker

    The Central government approved the construction of the 151.36 km Kothapalli-Manoharabad railway line on July 21, 2016. Initially, the project was estimated to cost ₹1,160.48 crore, but delays caused the cost to increase significantly. Bandi Sanjay shared that he had raised the issue with Prime Minister Narendra Modi and Union Railway Minister Ashwini Vaishnaw, who assured full support. “They emphasized completing pending projects before approving new ones and committed to allocating all necessary funds for such projects,” he said.

    Sanjay Kumar revealed that the revised cost of the project is now estimated at ₹2,780.78 crore, with ₹1,444.17 crore already spent. The state government is required to contribute one-third of the total project cost. So far, 76.135 km of the railway line has been completed, leaving around 75 km still under construction. For the 2024-25 financial year, ₹350 crore was allocated to the project, out of which ₹262.93 crore has already been utilized. The minister added, “Our target is to complete more than 30 km of railway construction in the Siddipet and Sircilla districts by September this year.”

    - Advertisement -

    Land acquisition for the railway line has been a significant challenge, but 90% of the required land has now been secured. Out of the total 1,145.627 hectares (around 2,830 acres) needed, 199 acres remain to be acquired. Additionally, 37.5 acres of forest land in the Rajanna Sircilla district need to be diverted, and efforts are underway to resolve this issue soon. The government aims to complete 31.06 km of construction from Vemulawada to Kothapalli by December 2023 and an additional 10.7 km in the Sircilla and Vemulawada areas by March 2026.

    Also read:  Rachakonda police restricts gatherings of over 5 near exam centers

    The tender process for the Siddipet-Sircilla section, spanning 76.13 km to 106.8 km, has been completed, and construction is progressing. “We plan to start new broad-gauge operations between Siddipet and Sircilla by December 2023,” the minister said. There are also plans to develop Kothapalli station into a junction with freight handling facilities, with operations expected to begin by March 2025.

    For the Sircilla-Vemulawada section, covering 106.8 km to 111.5 km, the project has reached the Engineering, Procurement, and Construction (EPC) stage. A key component of the project includes building a critical bridge over the Maneru River, which will ensure uninterrupted train travel on this route. The EPC tender process for the bridge is expected to begin by the end of the month, with the bridge playing a vital role in enhancing connectivity and easing train operations.

    Bandi Sanjay expressed confidence that the entire Kothapalli-Manoharabad railway line would be completed and operational by 2027. He noted that once operational, the railway line would drive development in the backward areas of Telangana, particularly in the Medak, Siddipet, Rajanna Sircilla, and Karimnagar districts. This railway line will provide people in these regions with improved access to rail travel. During his visit, the minister also inspected the ongoing modernisation works at Karimnagar Railway Station.

    - Advertisement -
    Rajesh M
    Rajesh Mhttps://www.telanganatribune.com
    Latest News from Hyderabad, Telangana, India & World!

    Follow us

    3,565FansLike
    179FollowersFollow
    1,202FollowersFollow
    965SubscribersSubscribe

    Contribute News

    You can contribute an article to Telangana Tribune by dropping a mail at newsdesk@telanganatribune.com

    Latest stories

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here